Energy Transmission

Project Expropriation Process

Project Expropriation Process

Determining of the transmission line paths
• TEİAŞ processes follow-up
• Route studies and measurements for 380 kV and 154 kV lines
• Making of plan, profile and distribution, and preparation of direct delivery list
• Selection of mast and mast locations and their approval by TEİAŞ
• Preparation of expropriation plans and their approval by TEİAŞ
• Field application and taking of pole foot N sections and approval by TEİAŞ